Every couple months, the City of Cupertino sends out an update on their progress with the Stevens Creek Corridor project. The current phase is taking place around McClellan Ranch and Blackberry farm. The creek itself is being re-routed to restore it to a more gentle slope, allowing removal of the rip-rap and concrete that was put in there 50 years ago when Blackberry Farm was built. In this installment, the focus is on changing the flow of the creek to the new channel, and the challenges of doing that. (Hint, the fish didn't get the memo, so they needed some assistance.) Read the PDF Newsletter here. Written by Webmaster Ross on 2009-1-30. |
posted at: 09:53 | path: | permanent link to this entry |
![]() |